Weekly Update 52

Internal

  • Casting of final infill sections of concrete slab (commencing 31.07.2023 for 1 week)
  • Cleaning main warehouse
  • Builders clean main office and toilet areas
  • Mastic (sealant) to all ground floor concrete expansion joints
  • High lever builders clean to main warehouse steel, cladding and roofing

External

  • Cleaning of main carpark ahead of final tarmac surface course (commencing 31.07.2023 for a 2.5 week duration)
  • Completing installation of external concrete yard infills (commencing 07.08.2023 for a 1 week duration)
  • Installation of lighting columns and wiring
  • Soft landscaping to all areas
  • Snagging to completed works

Get in Touch

If you have any questions or would like additional information, please get in touch in the following way:

We hold all personal data as per General Data Protection Regulation (GDPR) (EU) 2016/679 and your personal data will not be transferred outside of its jurisdiction. If you would like to make a GDPR request, please contact Lexington on 020 7025 2300. You can view our privacy policy here.
Alternatively, you can get in touch via the following: Email: faringtonconstruction@havingyoursay.co.uk