Main warehouse
- Electrical fitout works will continue to progress including external building mounted lighting.
- Install remainder of the perimeter doors.
- External cladding works to the East elevation will be ongoing .
Main Office
- Joinery final fix works will continue to progress with internal doors sets.
- Internal builders clean to all floors.
- Carpet installation to commence.
External works
- Timber close board Perimeter fencing works north-east boundary will continue.
- Acoustic fencing installation to commence north carpark perimeter.
- Hard landscaping works to include EV charges kerbing and landscaping works to continue to most of the external areas.