The construction works are nearing completion and detailed below is a summary of the activities to be carried out over the next week.
Internally
- Sparkle clean being carried out to main offices
- Final clean down and polish of internal warehouse concrete slab commenced
- Snagging being carried out to all internal areas of warehouse and main offices
Externally
- All tarmac works complete
- Road markings being completed to carpark
- All concrete works complete to service yard, mastic works to floor joints commenced during dry spell
- External lighting columns erected and now heads being fitted and tested
- Public right of way (Part 2) Footpath being installed along with lighting
- Landscaping being completed
- Fencing to main access road being installed
- Main site offices to be removed in approximately 2 weeks