Internal
- Casting of final infill sections of concrete slab
- Cleaning to main warehouse
- Builders clean to main office and toilet areas
- Mastic to all ground floor concrete expansion joints
- High lever builders clean to main warehouse steel, cladding and roofing
External
- Final tarmac surfacing to main carpark area
- Final tarmac surfacing to fire track road on the west and south elevations
- Completing installation of external concrete yard infills (Commencing 07.08.2023 for a 1 week duration)
- Installation of external lighting column heads
- Soft landscaping to all areas
- Installation of new canopy over level access doors
- Snagging to completed works
- Acoustic fencing install
Within the next 2 weeks numbers on site will be reduce and will predominantly be snagging then into Sept.