Weekly Update 53

Internal

  • Casting of final infill sections of concrete slab
  • Cleaning to main warehouse
  • Builders clean to main office and toilet areas
  • Mastic to all ground floor concrete expansion joints
  • High lever builders clean to main warehouse steel, cladding and roofing

External

  • Final tarmac surfacing to main carpark area
  • Final tarmac surfacing to fire track road on the west and south elevations
  • Completing installation of external concrete yard infills (Commencing 07.08.2023 for a 1 week duration)
  • Installation of external lighting column heads
  • Soft landscaping to all areas
  • Installation of new canopy over level access doors
  • Snagging to completed works
  • Acoustic fencing install

Within the next 2 weeks numbers on site will be reduce and will predominantly be snagging then into Sept.

Get in Touch

If you have any questions or would like additional information, please get in touch in the following way:

We hold all personal data as per General Data Protection Regulation (GDPR) (EU) 2016/679 and your personal data will not be transferred outside of its jurisdiction. If you would like to make a GDPR request, please contact Lexington on 020 7025 2300. You can view our privacy policy here.
Alternatively, you can get in touch via the following: Email: faringtonconstruction@havingyoursay.co.uk