Internal
- Casting of final infill sections of concrete slab (commencing 31.07.2023 for 1 week)
- Cleaning main warehouse
- Builders clean main office and toilet areas
- Mastic (sealant) to all ground floor concrete expansion joints
- High lever builders clean to main warehouse steel, cladding and roofing
External
- Cleaning of main carpark ahead of final tarmac surface course (commencing 31.07.2023 for a 2.5 week duration)
- Completing installation of external concrete yard infills (commencing 07.08.2023 for a 1 week duration)
- Installation of lighting columns and wiring
- Soft landscaping to all areas
- Snagging to completed works