Weekly Update 51

Main warehouse

  • Electrical fit out works will continue will continue this week. Works include external building mounted lighting and electrical testing.
  • Complete cladding works to southeast elevation including new level access doors.

Main Office

  • Joinery final fix works will continue with door sets, mirrors and final fixtures.
  • Floor finishes to all floors.
  • Final fix fire alarm.

External works

  • Acoustic fencing installation to north carpark perimeter and weld mesh fencing to west elevation.
  • Electric vehicle charges to carparks area.
  • Hard landscaping works to include EV charges kerbing and landscaping works to continue to most of the external areas.
  • Perimeter landscaping to all areas.

Get in Touch

If you have any questions or would like additional information, please get in touch in the following way:

We hold all personal data as per General Data Protection Regulation (GDPR) (EU) 2016/679 and your personal data will not be transferred outside of its jurisdiction. If you would like to make a GDPR request, please contact Lexington on 020 7025 2300. You can view our privacy policy here.
Alternatively, you can get in touch via the following: Email: faringtonconstruction@havingyoursay.co.uk