Weekly Update 50

Main warehouse

  • Electrical fitout works will continue to progress including external building mounted lighting.
  • Install remainder of the perimeter doors.
  • External cladding works to the East elevation will be ongoing .

Main Office

  • Joinery final fix works will continue to progress with internal doors sets.
  • Internal builders clean to all floors.
  • Carpet installation to commence.

External works

  • Timber close board Perimeter fencing works north-east boundary will continue.
  • Acoustic fencing installation to commence north carpark perimeter.
  • Hard landscaping works to include EV charges kerbing and landscaping works to continue to most of the external areas.

Get in Touch

If you have any questions or would like additional information, please get in touch in the following way:

We hold all personal data as per General Data Protection Regulation (GDPR) (EU) 2016/679 and your personal data will not be transferred outside of its jurisdiction. If you would like to make a GDPR request, please contact Lexington on 020 7025 2300. You can view our privacy policy here.
Alternatively, you can get in touch via the following: Email: faringtonconstruction@havingyoursay.co.uk